Case Study

Heritage roof refurbishment at Tower Bridge

Heritage roof refurbishment at Tower Bridge

Garland System

Dura-Coat

Single-Point Guarantee

20 Years

As one of the UK’s most iconic and historically significant structures, Tower Bridge is a Grade I listed site that demands the highest standards in conservation, safety, and technical delivery. As part of a planned heritage maintenance programme, the client identified that three independent external ticket office roofs, located at the north and south approaches, had reached the end of their serviceable life. The original asphalt waterproofing, installed in the 1960s, had deteriorated and required replacement to ensure continued weatherproofing.

The project demanded a carefully considered solution that would respect the building’s protected status, retain the visual character of the existing roofs, and be installed without disrupting the bridge’s operational function. Working in a live public environment with significant pedestrian footfall added further complexity, as did the requirement to avoid hot works and maintain the original light grey reflective finish.

Garland UK was appointed as system designer and material supplier, with Technical Manager Jack Costello overseeing the specification, detailing and technical support throughout the works. Installation was delivered by Garland UK Approved Contractor JAW Roofing, working under Garland’s quality-assured partnership model.

Solution

Garland UK specified the Dura-Coat liquid waterproofing system, a high-performance polyurethane-modified methyl methacrylate (PMMA) solution engineered to provide durable waterproofing over existing substrates, including aged asphalt. This made it an ideal match for the ticket office roofs, where retention of the existing structure was a conservation requirement.

The system offered several critical advantages. Its flame-free, cold-applied application removed the need for hot works and eliminated associated risks within a live public setting. Dura-Coat’s rapid curing properties ensured reliable installation even in lower temperatures, with catalyst levels adjusted daily to suit site conditions. Crucially, the system build-up allowed for direct application to the cleaned asphalt substrate without any alteration to existing thresholds or parapet levels.

The full system included Garland Dura-Coat Primer, an embedment coat, reinforcement fleece, and a colour-matched light grey topcoat to replicate the original solar-reflective finish. All materials were fully compatible with the existing asphalt, and designed to deliver long-term waterproofing with minimal environmental impact. The system, supplied in full by Garland UK, ensured complete technical continuity and traceability.

Throughout the programme, Garland UK provided close technical oversight, reviewing detailed drawings and advising on sequencing, termination accuracy and quality assurance. Jack Costello conducted regular site visits, offering practical guidance to support the contractor during cold-weather work and overseeing key detailing to ensure full compliance with the agreed specification. The works were tracked using Garland UK’s Roof Asset Management Programme (RAMP), providing progress reports and photographic documentation as a digital audit trail for stakeholder transparency.

The insulation build-up was increased to 150mm PIR, improving the roof U-value from 0.24 W/m²K to 0.10 W/m²K. This step change in thermal performance directly reduced heat loss and supported the wider low-carbon heat strategy being introduced across the estate.

Garland UK Technical Manager Dan Crowley provided ongoing support from initial survey to on-site project delivery, working closely with other trades and stakeholders to resolve challenges as they arose and keep the programme moving.

Heritage roof refurbishment at Tower Bridge

Garland Technical Manager

Approved Contractor

  • JAW Roofing

As one of the UK’s most iconic and historically significant structures, Tower Bridge is a Grade I listed site that demands the highest standards in conservation, safety, and technical delivery. As part of a planned heritage maintenance programme, the client identified that three independent external ticket office roofs, located at the north and south approaches, had reached the end of their serviceable life. The original asphalt waterproofing, installed in the 1960s, had deteriorated and required replacement to ensure continued weatherproofing.

Quick Facts

Garland System
Sector

Residential

Single-Point Guarantee

20 Years

The storm exposed critical weaknesses in the original roof design, which had failed to cope with the site’s wind load demands. The closure meant immediate loss of revenue, reduced access to community leisure facilities, and growing urgency to reopen.

The replacement roof required complex engineering to match the building’s 40 metre wide dual-curved structure. Standing seam sheets up to 22 metres in length had to be precision-engineered off-site, with escorted delivery, timed road closures, and careful sequencing of work.

With only a small car park as the site compound, storage, crane operations, and contractor access needed meticulous planning. Moisture protection for the exposed structure was critical throughout, with temporary coverings installed until the new system could be sealed.

Garland UK Technical Manager Rob Wall specified the R-MER LOC standing seam metal system, designed for storm resilience, thermal efficiency, and long service life in marine climates. Its penetration-free, zip-free seam design enabled faster installation and allowed for thermal movement without panel distortion.

The system was tailored to the building’s complex geometry, with 22 metre top sheet runs and 18 metre lower runs. Approved contractor, Future Roof Leeds, carried out the works, reusing the existing perforated aluminium liner where possible to reduce waste and disruption.

A high-performance, foil-lined vapour control layer was installed, along with upgraded insulation and a breather membrane suitable for coastal exposure. Acoustic infills were also integrated to maintain internal sound control, enhancing the original system’s acoustic performance.

 

The 1,200 sqm roofing system was completed on time and within budget, restoring full functionality to SC2 Water Park and preventing further loss of income. Garland UK’s Roof Asset Management Programme (RAMP) now provides the Council with a complete digital record of the project, including inspection reports, guarantees, and maintenance guidance, giving estates teams full visibility for ongoing asset care.

Covered by a 30 year Single-Point Guarantee for design, materials, and workmanship, the Council has complete assurance that any issues will be resolved swiftly, without dispute or additional cost.

The reopening of SC2 Water Park has reinstated a much-loved leisure venue for residents and visitors, supporting local wellbeing, tourism, and economic activity. The storm-resilient design means fewer disruptions and reduced maintenance, and reliable year-round availability, even in challenging weather.

Robin Jones, Senior Building Surveyor at Denbighshire County Council, commented,

“The level of service from Garland UK has been first-class from start to finish. Rob and the team gave us confidence at every stage, from design to handover. The quality of the roof and the management of such a tricky site exceeded our expectations.”

Rob Wall, Technical Manager at Garland UK, added,

“This was a demanding brief in a harsh environment. The combination of curved geometry, extreme sheet lengths and complex logistics called for precision planning and strong collaboration. We’re proud to have supported the Council in getting this key venue back up and running.”