Case Study

Targeted Roof Retention Saves £150,000 at Riverside Mansions

Targeted Roof Retention Saves £150,000 at Riverside Mansions

Garland System

Dura-Coat

Sector

Residential

Project Cost Saving

£150,000

Riverside Mansions is a large-scale residential block in London with approximately 3,500 m² of flat roofing and 1,500 m² of communal walkways and balconies. The project required a roof retention refurbishment for a residential block, enabling the client, a chartered surveying practice with an established relationship with Garland UK, to move away from reactive repairs and escalating costs for the building owners.

The roof had last been refurbished around 14 years prior to Garland UK’s involvement. Despite ongoing patch repairs, persistent water ingress remained a concern. The client required a long-term, future-proofed solution that avoided full strip-out while delivering cost certainty and value for the asset.

Garland UK Technical Manager Alex Kitis carried out a detailed roof condition survey across the site. To eliminate assumptions and reduce financial risk, Garland UK instructed independent moisture scanning by RWS. The data results confirmed that only 11% of the roof area required a full strip and repair. Over 89% of the existing roof remained serviceable.

This evidence-based approach directly influenced the specification strategy, allowing the majority of the roof to be retained and avoiding unnecessary replacement works. As a result, Riverside Mansions achieved approximately £150,000 in savings through reduced labour and disposal costs alone.

Solution

Garland UK developed a targeted retention-led specification centred on retention, speed and cost control. Saturated areas identified during the detailed roof condition report and moisture survey were stripped back and replaced. The remaining sound areas were prepared and overlaid using Dura-Coat, Garland’s cold-applied liquid waterproofing system.

Existing insulation already met Part L requirements, eliminating the need for costly thermal upgrades and further reducing project cost. This allowed the specification to concentrate on waterproofing performance and system longevity.

Dura-Coat’s fast-curing properties played a key role in the project’s success. The system allowed walkways to reopen within a couple of hours, maintaining resident access and avoiding extended closures. This reduced disruption and prevented the indirect costs often associated with residential refurbishment projects.

For balconies and communal walkways, Garland UK specified the Dura-Walk system. Approximately 1,500 m² of walkways and balconies were refurbished. Adhesion testing was carried out prior to installation due to previous low-level liquid applications showing early signs of failure. The new Dura-Walk system delivered a durable, anti-slip finish suitable for both private balconies and high-traffic communal areas.

Targeted Roof Retention Saves £150,000 at Riverside Mansions

Garland Technical Manager

Approved Contractor

  • London Seamless Flat Roofing

Riverside Mansions is a large-scale residential block in London with approximately 3,500 m² of flat roofing and 1,500 m² of communal walkways and balconies. The project required a roof retention refurbishment for a residential block, enabling the client, a chartered surveying practice with an established relationship with Garland UK, to move away from reactive repairs and escalating costs for the building owners.

The roof had last been refurbished around 14 years prior to Garland UK’s involvement. Despite ongoing patch repairs, persistent water ingress remained a concern. The client required a long-term, future-proofed solution that avoided full strip-out while delivering cost certainty and value for the asset.

Quick Facts

Garland System
Sector

Residential

Project Saving Cost

£150,000

The storm exposed critical weaknesses in the original roof design, which had failed to cope with the site’s wind load demands. The closure meant immediate loss of revenue, reduced access to community leisure facilities, and growing urgency to reopen.

The replacement roof required complex engineering to match the building’s 40 metre wide dual-curved structure. Standing seam sheets up to 22 metres in length had to be precision-engineered off-site, with escorted delivery, timed road closures, and careful sequencing of work.

With only a small car park as the site compound, storage, crane operations, and contractor access needed meticulous planning. Moisture protection for the exposed structure was critical throughout, with temporary coverings installed until the new system could be sealed.

Garland UK Technical Manager Rob Wall specified the R-MER LOC standing seam metal system, designed for storm resilience, thermal efficiency, and long service life in marine climates. Its penetration-free, zip-free seam design enabled faster installation and allowed for thermal movement without panel distortion.

The system was tailored to the building’s complex geometry, with 22 metre top sheet runs and 18 metre lower runs. Approved contractor, Future Roof Leeds, carried out the works, reusing the existing perforated aluminium liner where possible to reduce waste and disruption.

A high-performance, foil-lined vapour control layer was installed, along with upgraded insulation and a breather membrane suitable for coastal exposure. Acoustic infills were also integrated to maintain internal sound control, enhancing the original system’s acoustic performance.

 

The 1,200 sqm roofing system was completed on time and within budget, restoring full functionality to SC2 Water Park and preventing further loss of income. Garland UK’s Roof Asset Management Programme (RAMP) now provides the Council with a complete digital record of the project, including inspection reports, guarantees, and maintenance guidance, giving estates teams full visibility for ongoing asset care.

Covered by a 30 year Single-Point Guarantee for design, materials, and workmanship, the Council has complete assurance that any issues will be resolved swiftly, without dispute or additional cost.

The reopening of SC2 Water Park has reinstated a much-loved leisure venue for residents and visitors, supporting local wellbeing, tourism, and economic activity. The storm-resilient design means fewer disruptions and reduced maintenance, and reliable year-round availability, even in challenging weather.

Robin Jones, Senior Building Surveyor at Denbighshire County Council, commented,

“The level of service from Garland UK has been first-class from start to finish. Rob and the team gave us confidence at every stage, from design to handover. The quality of the roof and the management of such a tricky site exceeded our expectations.”

Rob Wall, Technical Manager at Garland UK, added,

“This was a demanding brief in a harsh environment. The combination of curved geometry, extreme sheet lengths and complex logistics called for precision planning and strong collaboration. We’re proud to have supported the Council in getting this key venue back up and running.”