Case Study

Fabric-first retrofit supporting RNCM’s decarbonisation strategy

Fabric-first retrofit supporting RNCM’s decarbonisation strategy

Garland System

StressPly Flex Plus

Sector

Education

U-value Achieved

0.10 W/m²K

Energy Savings

300,000 kWh

The Royal Northern College of Music (RNCM) undertook a major decarbonisation programme while remaining fully operational, placing significant pressure on its existing building fabric to perform better, not just differently. With energy demand rising and long-term resilience a priority, a fabric-first approach sat at the heart of the strategy, with the roof identified as a critical opportunity to deliver meaningful and measurable thermal performance gains.

Garland UK was appointed as technical roofing partner to support the refurbishment of multiple roof areas as part of a wider Salix-funded programme, with Dodd Group appointed as main contractor, coordinating the multi-trade environment across the live campus. Working closely with Dr John Hindley, Director at Twelvetrees Consulting, the RNCM estates team and the wider design team, Garland UK provided system design, thermal performance support and on-site technical leadership to ensure the roof retrofit contributed directly to the college’s decarbonisation objectives.

Solution

Garland UK worked as both a technical roofing expert and active decarbonisation partner, supporting the client-led strategy while influencing key performance, system, and delivery decisions. The roofing works were installed by Absolute Waterproofing, a Garland UK Approved Contractor, working under Garland UK’s technical oversight and quality assurance regime to ensure the system was installed in line with the design intent and performance requirements.

The existing standing seam roof was overlaid with a three-layer StressPly Flex Plus bituminous membrane system, selected for its durability, detailing capability and speed of installation. This approach avoided unnecessary stripping out, reduced waste and allowed progress to be maintained despite heavy roof traffic and ongoing plant movements.

Working closely with Ian Palmer Architects, Garland UK supported design development and detailing, ensuring interfaces with plant, edge protection systems and drainage were resolved without compromising waterproofing integrity or thermal continuity.

The insulation build-up was increased to 150mm PIR, improving the roof U-value from 0.24 W/m²K to 0.10 W/m²K. This step change in thermal performance directly reduced heat loss and supported the wider low-carbon heat strategy being introduced across the estate.

Garland UK Technical Manager Dan Crowley provided ongoing support from initial survey to on-site project delivery, working closely with other trades and stakeholders to resolve challenges as they arose and keep the programme moving.

Fabric-first retrofit supporting RNCM’s decarbonisation strategy

Garland Technical Manager

Approved Contractor

  • Absolute Waterproofing

The Royal Northern College of Music (RNCM) undertook a major decarbonisation programme while remaining fully operational, placing significant pressure on its existing building fabric to perform better, not just differently. With energy demand rising and long-term resilience a priority, a fabric-first approach sat at the heart of the strategy, with the roof identified as a critical opportunity to deliver meaningful and measurable thermal performance gains.

Quick Facts

Garland System
Sector

Residential

Project Saving Cost

£900,000

The storm exposed critical weaknesses in the original roof design, which had failed to cope with the site’s wind load demands. The closure meant immediate loss of revenue, reduced access to community leisure facilities, and growing urgency to reopen.

The replacement roof required complex engineering to match the building’s 40 metre wide dual-curved structure. Standing seam sheets up to 22 metres in length had to be precision-engineered off-site, with escorted delivery, timed road closures, and careful sequencing of work.

With only a small car park as the site compound, storage, crane operations, and contractor access needed meticulous planning. Moisture protection for the exposed structure was critical throughout, with temporary coverings installed until the new system could be sealed.

Garland UK Technical Manager Rob Wall specified the R-MER LOC standing seam metal system, designed for storm resilience, thermal efficiency, and long service life in marine climates. Its penetration-free, zip-free seam design enabled faster installation and allowed for thermal movement without panel distortion.

The system was tailored to the building’s complex geometry, with 22 metre top sheet runs and 18 metre lower runs. Approved contractor, Future Roof Leeds, carried out the works, reusing the existing perforated aluminium liner where possible to reduce waste and disruption.

A high-performance, foil-lined vapour control layer was installed, along with upgraded insulation and a breather membrane suitable for coastal exposure. Acoustic infills were also integrated to maintain internal sound control, enhancing the original system’s acoustic performance.

 

The 1,200 sqm roofing system was completed on time and within budget, restoring full functionality to SC2 Water Park and preventing further loss of income. Garland UK’s Roof Asset Management Programme (RAMP) now provides the Council with a complete digital record of the project, including inspection reports, guarantees, and maintenance guidance, giving estates teams full visibility for ongoing asset care.

Covered by a 30 year Single-Point Guarantee for design, materials, and workmanship, the Council has complete assurance that any issues will be resolved swiftly, without dispute or additional cost.

The reopening of SC2 Water Park has reinstated a much-loved leisure venue for residents and visitors, supporting local wellbeing, tourism, and economic activity. The storm-resilient design means fewer disruptions and reduced maintenance, and reliable year-round availability, even in challenging weather.

Robin Jones, Senior Building Surveyor at Denbighshire County Council, commented,

“The level of service from Garland UK has been first-class from start to finish. Rob and the team gave us confidence at every stage, from design to handover. The quality of the roof and the management of such a tricky site exceeded our expectations.”

Rob Wall, Technical Manager at Garland UK, added,

“This was a demanding brief in a harsh environment. The combination of curved geometry, extreme sheet lengths and complex logistics called for precision planning and strong collaboration. We’re proud to have supported the Council in getting this key venue back up and running.”