Garland UK Technical Manager
Alex Kitis
Approved Contractor
Evolution Contracts
Garland System
Dura-Coat
Sector
Healthcare
Project Cost Saving
£900,000
Located in Enfield, the Cavell Hospital is a key facility for Circle Health Group. Spanning over 1,000 square metres, the building’s existing mastic asphalt roof had reached a critical state of disrepair, causing water ingress and internal damage. Faced with a significant refurbishment challenge, Circle Health Group turned to its long-term partner, Garland UK, to deliver a durable and cost-effective hospital roof upgrade that aligned with stringent budget constraints and compliance standards.
Garland UK’s technical team, led by Technical Manager Alex Kitis, implemented a service-led approach starting with a detailed roof condition survey that provided clear and accurate data for targeted specification. A comprehensive moisture scan was conducted, precisely mapping areas of saturation. This revealed that only 20% of the roof required full strip and replacement, while under 50% of the existing substrate could be retained under building control repair rules, avoiding a full thermal upgrade.
Crucially, this survey enabled the project to proceed with minimal disturbance to the plant equipment. Instead of a full removal, which would have added approximately £1 million to the budget, strategic isolation of plant units allowed for works to proceed with only minor relocation. This reduced plant-related costs to under £100,000, a saving of over 90%. These savings were made possible by the Dura-Coat system’s ability to be easily applied under and around complex plant penetrations without the need for disassembly, making it ideal for intricate roof layouts with heavy detailing.
The Garland-specified Dura-Coat PUMA liquid waterproofing system was the ideal solution for overlaying the remaining sections of the existing roof, thanks to its effective crack-bridging properties and rapid 30-minute curing time. For stripped areas, a new build-up incorporating a vapour barrier and 120mm PIR infill insulation with tapered insulation to the gutters was installed to promote water runoff through the congested internal gutters.
Installed by Approved Contractor, Evolution Contracts, the system provided a seamless, high-performance waterproofing layer with superior flexibility and durability, perfectly suited to the busy hospital environment. All works were fully monitored under Garland UK’s rigorous quality assurance program, with twice-weekly site inspections and full digital reporting via the RAMP (Roof Asset Management Programme) portal.
For balconies and communal walkways, Garland UK specified the Dura-Walk system. Approximately 1,500 m² of walkways and balconies were refurbished. Adhesion testing was carried out prior to installation due to previous low-level liquid applications showing early signs of failure. The new Dura-Walk system delivered a durable, anti-slip finish suitable for both private balconies and high-traffic communal areas.