Case Study

Storm-Resilient Metal Roofing Restores Leisure Centre

Storm-Resilient Metal Roofing Restores Leisure Centre

Garland System

Solarise

Sector

Industrial

Year 1 Energy Saving

£13,500

Avoided to Landfill

37 tonnes

Payback

6 years

Temp Image 2

Introduction

At Hambridge Industrial Estate in Newbury, Greenham Common Trust needed to act quickly to secure the future of one of its key commercial units. The asbestos cement roof was over 30 years old, leaking, and no longer safe.

The client had been working with Garland UK since 2015 and trusted us to deliver a long-term solution. With tenant agreements up for renewal, a durable roof refurbishment was essential to keep valued tenants in place. At the same time, the client wanted to cut electricity costs and strengthen the building’s energy performance by investing in solar.

Temp Image 2

Solution

Technical Manager Daniel Sandell specified the R-MER CLAD system to overclad the asbestos roof. This avoided a costly strip-out while encapsulating the asbestos safely and eliminating the risk of fibre release. For the client, this meant work could be carried out without the disruption of full asbestos removal, keeping tenants secure in their units.

A new vapour control layer and supporting frame were installed, followed by high-performance mineral quilt insulation to meet the 0.18W/m²K target. The new profiled metal sheets were secured with stainless steel fixings and sealed at laps to ensure a watertight finish. Gutters were refurbished with a liner system to further protect the building envelope. The outcome was a future-proofed roof that complies with Part L, reduces heating bills, and lowers carbon emissions.

Once the new roof was in place, Nimbus Solar installed a 149.52kWp Solarise PV system, rail-mounted onto the R-MER CLAD sheets. The array of 336 Solarwatt panels will generate an estimated 145,500 kWh of electricity each year, meeting around 63% of the building’s demand. The system is forecast to achieve payback in under six years, and generate an accrued cash flow of over £1.2m across 25 years.

With Solarwatt panels offering a 25 year system life, the client can be confident that the solar system will continue to perform for decades, supported by Garland UK’s roof-first approach. Both the roof and solar system are covered under a 20 year Single-Point Guarantee, ensuring no split liability and complete protection for the investment.

R0MER LOC storm-resilient roof securing SC2 Water Park community facility

Storm-Resilient Metal Roofing Restores Leisure Centre

Garland Technical Manager

Approved Contractor

  • Future Roof Leeds

SC2 Water Park in Rhyl, a flagship leisure destination for Denbighshire County Council, faced an unexpected crisis when severe storms ripped off the original roof. With the previous manufacturer no longer trading, the Council needed an experienced, technically capable partner who could restore the site quickly and ensure it was protected for decades to come.

Already a trusted supplier to the Council, Garland UK was appointed to design and deliver a bespoke, long-term roofing solution capable of withstanding the demanding coastal environment and safeguarding this key community facility.

Quick Facts

Garland System
Sector

Public

Size

1,200 sqm

Single-Point Guarantee

30 year

The storm exposed critical weaknesses in the original roof design, which had failed to cope with the site’s wind load demands. The closure meant immediate loss of revenue, reduced access to community leisure facilities, and growing urgency to reopen.

The replacement roof required complex engineering to match the building’s 40 metre wide dual-curved structure. Standing seam sheets up to 22 metres in length had to be precision-engineered off-site, with escorted delivery, timed road closures, and careful sequencing of work.

With only a small car park as the site compound, storage, crane operations, and contractor access needed meticulous planning. Moisture protection for the exposed structure was critical throughout, with temporary coverings installed until the new system could be sealed.

Garland UK Technical Manager Rob Wall specified the R-MER LOC standing seam metal system, designed for storm resilience, thermal efficiency, and long service life in marine climates. Its penetration-free, zip-free seam design enabled faster installation and allowed for thermal movement without panel distortion.

The system was tailored to the building’s complex geometry, with 22 metre top sheet runs and 18 metre lower runs. Approved contractor, Future Roof Leeds, carried out the works, reusing the existing perforated aluminium liner where possible to reduce waste and disruption.

A high-performance, foil-lined vapour control layer was installed, along with upgraded insulation and a breather membrane suitable for coastal exposure. Acoustic infills were also integrated to maintain internal sound control, enhancing the original system’s acoustic performance.

 

The 1,200 sqm roofing system was completed on time and within budget, restoring full functionality to SC2 Water Park and preventing further loss of income. Garland UK’s Roof Asset Management Programme (RAMP) now provides the Council with a complete digital record of the project, including inspection reports, guarantees, and maintenance guidance, giving estates teams full visibility for ongoing asset care.

Covered by a 30 year Single-Point Guarantee for design, materials, and workmanship, the Council has complete assurance that any issues will be resolved swiftly, without dispute or additional cost.

The reopening of SC2 Water Park has reinstated a much-loved leisure venue for residents and visitors, supporting local wellbeing, tourism, and economic activity. The storm-resilient design means fewer disruptions and reduced maintenance, and reliable year-round availability, even in challenging weather.

Robin Jones, Senior Building Surveyor at Denbighshire County Council, commented,

“The level of service from Garland UK has been first-class from start to finish. Rob and the team gave us confidence at every stage, from design to handover. The quality of the roof and the management of such a tricky site exceeded our expectations.”

Rob Wall, Technical Manager at Garland UK, added,

“This was a demanding brief in a harsh environment. The combination of curved geometry, extreme sheet lengths and complex logistics called for precision planning and strong collaboration. We’re proud to have supported the Council in getting this key venue back up and running.”

Garland UK
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.